SKIP TO CONTENT
USE CASE 06 · FOUNDRY · SAND CASTING · ONE QUARTER

83 hours of lost production a quarter, about 57,000 inserts, cut by roughly 90%.

IMPACT
  • 83 hours of lost production a quarter cut by roughly 90%
  • About 57,000 inserts no longer lost
  • Some months ran downtime-free
THE OPERATION
Industry
Foundry and casting
System type
Identical units, one goal
Machines
A 45 kW sand mixer, pumps, conveyors and more
Period
A quarter
01 · What the operation faced

A 6,000 tonne-a-year sand-casting foundry built around a 45 kW sand mixer, plus pumps, conveyors, sieves, vibro motors, exhaust fans, shot blasts and cranes.

Airborne sand, heat, impact loading and electromagnetic interference defeat conventional sensing through sensor failure, cabling and poor machine access.

02 · What minto.ai held and reasoned across

Mapping load paths and drive-train mechanics against fault history showed that instrumenting under half the machines would head off around 80% of unplanned stoppages.

Nothing lives on the machine: the device reads from the cabinet, out of the sand, past the interference.

What changed

A quarterly 83 hours of lost production — about 57,000 inserts — was cut by roughly 90%, with some months running downtime-free.

Who it was forA rail-sleeper insert foundry